Notes:
7/3/2025 10:00:16 AM
Updated from permit [INSERT] to include reasoning behind why 2 lanes are needed to be closed on H and G streets as well as approximate durations of closures.
7/16/2025 7:56:58 AM
Phased traffic control plan to encroach G, 10th and H streets in order to repave the portions of the aforementioned streets per the approved project plans. The first phase will close 2 lanes of travel for one block along H street as well as 1 block of 10th street. The seconf phase will close 2 lanes of travel along G street. Each phase will have a duration of 9 weeks.
7/16/2025 8:01:09 AM
TIME & MATERIAL
Max Navarro
TRAFFIC CONTROL 1ST SUBMITTAL
Provide notification to emergency response, fire and MPD. Notify businesses within the taper area of the lane closure.
7/9/2025 7:41:49 AM