Notes:
1/15/2025 7:34:13 AM
Repair asphalt that was disturbed during emergency work
1/16/2025 12:25:48 PM
Excavation in newly renovated City streets is prohibited for three (3) years after filing of a notice of completion or acceptance of a new street or structural overlay of an entire street except as follows:
Emergency which endangers life or property;
Repair or modification to prevent denial or interruption of utility service;
Relocation work that is mandated by City, State or Federal legislation;
Service for buildings where no other reasonable means of providing service exists, as determined by the Director;
In a City street that the City has scheduled for resurfacing either during the fiscal year (July 1 - June 30) when the excavation permit is issued or during the immediately following fiscal year and the work takes place prior to the resurfacing;
For potholing to verify utility depth or location;
Horizontal Directional Drilling (HDD) excavations greater than eighteen (18) inches in depth of cover over the utility facility not requiring a significant surface incision greater than four (4) square feet and at a depth not greater than six (6) inches below the asphalt may be allowed at the discretion of the Director;
Other situations deemed by the Director to be in the best interest of the general public.